Foundations

New build house - Little Wenlock, Shropshire

As featured on Living The Dream - Series 2, Episode 1

Project duration: 20 weeks (to ground level)
Project Overview:

• Establish the site for overall house build.
• Set out foundations
• Form swimming pool and basement
• Take up form work and cast walls up to ground floor level
• Lay floor beams as oversite


Superstructure

New build 6 bedroom holiday cottage - Nr Bridgnorth, Shropshire

Project duration: 40 weeks

Project Overview:

• Greenfield site build of 3,000 sq ft cottage.
• A mix of stone, brickwork, and timber cladding.
• All rooms fitted to letting standard,
  incl 6 x en-suite bedrooms, including ground floor
  disabled accommodation.
• Complete design and build package.
residential
NHBC registered for over 20 years

The construction skills required in industry apply equally to building a house. JSR know the importance of getting the substructure right, and so provide expertise in setting out foundations and drainage, and floor laying. They have taken this through to complete build of houses, garages, and swimming pools.
case studies
Powered by Camelot Media Ltd
Telephone: 01746 862786

Mobile: 07973 924730

Email: john@jsrconstruction.co.uk
Email: enquiries@jsrconstruction.co.uk
JSR Construction
Hill Farm
Chelmarsh
Bridgnorth
Shropshire
WV16 6AX